The two weeks we skipped
Why discovery done in silos, without the people who build the software in the room, is the biggest single reason software projects miss, and what two weeks together up front would have bought.
Most software projects that fail were set up to fail before anyone wrote any code. The engineers are rarely the problem. The problem is that nobody sat the people who decide what to build in a room with the people who build it, and agreed what was possible, before the deadline was set.
I am working on a project like that now. It is a useful example because nothing about it is unusual. Every organisation I have worked with has run at least one project this way.
How it started
The product needs changes from three engineering teams. Those teams report to one engineering manager. A product manager owns the outcome, and does not have a software background. That is common, and it is not a failing on their part. It means the process has to supply what experience would otherwise supply, and here there was no process.
The deadline was set first. The scope was described afterwards, in broad terms. Nobody estimated the work before committing to the date. Each team was handed its piece and started on it.
There was no plan, no timeline and no coordination between the teams. Nobody decided not to have them. Nobody’s job included making them exist.
Discovery happened, just in silos
It would be wrong to say there was no discovery. There was plenty. It happened in separate places:
- Product worked out what customers wanted, without engineering in the room to say what that would cost or what was already half-built.
- Each engineering team worked out how to build its own part, without seeing the other two teams’ parts or how they had to fit together.
- The engineering manager was left to discover the dependencies between teams as they collided, one at a time, usually in a status meeting.
Three groups each learned a third of what the project needed to know, and nobody put the three thirds together. That is the same as having no discovery at all, except it feels like progress.
What that costs
Goals nobody can align on. “Deliver the new product by the deadline” is not a goal three teams can align on, because each one reads it differently. One team builds for completeness, one for speed, and one waits for an API that another team has not started. Everyone works hard and the pieces still do not meet.
A deadline nobody tested. A date set before anyone estimates the work is a guess. When it turns out short, there is nowhere to move. Cutting scope is now a negotiation under pressure instead of a decision made calmly at the start.
One person as the only integration point. With three teams and no shared plan, every cross-team question goes through the engineering manager. One person becomes the coordination layer for a whole product, and every decision waits in their queue.
A structure you cannot change in time. The real fix is a cross-functional team built around the product, not three teams built around their existing systems. Reorganising takes longer than the deadline allows, so the project is stuck with the structure it has. As Conway’s law predicts, the software is coming out shaped like the org chart: three parts that meet awkwardly at the seams.
An outcome customers will not like. Given the time left, the teams can deliver something, but not something customers will be happy with. That is not because anyone worked slowly. The project used the time it had building parts that did not fit, and it is too late to recover that time.
What two weeks would have bought
If the product manager, the engineering manager, a lead from each team and someone close to the customers had spent two weeks together before work started, the project would have come out of it with:
- One goal everyone reads the same way, with a measure of success the customer would recognise.
- A map of the dependencies between the three teams, drawn before they started blocking each other.
- Estimates from the people doing the work, and so a deadline that was tested rather than assumed.
- A deliberate choice about scope. If the date is fixed, scope is the variable. Deciding what to leave out in week two is a design decision. Deciding it in the last month is triage.
- An agreed way of working across teams: one backlog, one demo, a regular point where the pieces are integrated, and a clear answer to who decides when teams disagree.
Two weeks is about five percent of a nine-month project. It is a small fraction of the time this project will lose to rework, waiting and integration problems.
It is a communication problem, not a people problem
Nobody on this project is incompetent. Nobody in the room was missing knowledge the project needed. The knowledge was spread across people who were never in the same room at the same time. The organisation had no habit of putting product and engineering together before committing to a plan, so it did not happen.
That is why I think siloed discovery is the biggest single blocker to project success. Bad technology choices, missed estimates and unclear requirements all do damage, but they are usually symptoms of it. When the people who decide and the people who build work out the plan together, those problems get caught in the first two weeks, when they are cheap.
If you are already in it
You cannot get the two weeks back, but you can still get some of their value:
- Hold a short inception now. Two days with the same people is better than none. Agree the one outcome that matters most and what you will stop doing to protect it.
- Draw the dependency map. Put every cross-team handoff on one page with a date, and review it weekly in front of all three teams.
- Tell customers early. If the deadline will not produce what they expect, they would rather hear it now, with a plan, than at the end.
- Write down what you learned. The next project will start the same way unless someone changes how projects start.
How to run a two-week inception covers how to structure those two weeks, who should be in the room, and what should come out of it.
If you are about to start a project that spans several teams, or you are already in one that feels like this, this is the kind of work I do. Email hello@byrenhigg.in with a few lines on where things stand.