How to run a two-week inception

A practical plan for two weeks of discovery and inception that gets product, engineering and the business agreeing on a goal, a scope and a timeline before a multi-team software project starts.

The two weeks we skipped is about what happens when a project starts without the people who decide and the people who build ever planning together. This post is the practical half: how to run those two weeks.

Inception and discovery mean different things in different places. Here, discovery is the first week: understanding the problem, the customers and the constraints. Inception is the second: turning that understanding into a goal, a scope and a plan everyone has agreed to. They work best back to back, with the same people.

Who is in the room

Keep it small enough to talk and broad enough that nobody has to go and ask someone else:

  • The product manager, who owns the what and the why.
  • A technical lead from every engineering team that will touch the product. Not just the manager. The people who know where the hard parts are.
  • The engineering manager, who owns how the teams work together.
  • Design, if the product has a user interface.
  • Someone who talks to customers every week, such as support, sales or account management.
  • The person who can move the deadline or the budget, for at least the first and last day. If nobody in the room can change the date, the room cannot make a real plan.

“In the room” can be a video call, but it has to be the same time and most of the day. Sending documents around for comment is how discovery ends up in silos.

Week one: discovery

Day 1: the problem and the outcome. Start with why the project exists. Who is it for, what are they struggling with now, and how would you know a year from now that it worked? End the day with one sentence describing the outcome and one or two measures of it. If the room cannot agree on that sentence, stop and fix it before you do anything else.

Day 2: customers and current state. Walk through what customers do today, step by step, using real examples from the person who talks to them. Then walk through the current systems that support it. Engineers often learn more about the product here than in a year of tickets, and the product manager often learns why something “simple” is not.

Days 3 and 4: constraints and unknowns. List what is fixed: deadlines, contracts, regulations, systems that cannot change. List what nobody knows yet, and give the engineers time to answer the biggest unknowns with short spikes: a day or two of throwaway code to find out whether something is possible, not to build it.

Day 5: the dependency map. Put every piece of work on a wall, colour-coded by team, and draw a line wherever one team needs something from another. This is the most valuable hour of the two weeks on a multi-team project. Every line is a future delay unless someone plans it.

Week two: inception

Day 6: options. There is almost always more than one way to deliver the outcome. Sketch two or three, including at least one much smaller than what was first imagined, and talk through the cost and risk of each.

Day 7: scope. Pick an option, then split its features into what must ship for the outcome to happen, what should ship if there is time, and what will not ship. Be specific. Everything in the third list is a decision the room made deliberately, which is very different from something that quietly did not get done.

Day 8: slices and estimates. Break the must-haves into thin slices that each work end to end across all the teams involved, rather than one layer from each team. Each slice should be something you could demonstrate. The people who will build each slice estimate it, as a range rather than a single number.

Day 9: the plan. Sequence the slices, put the cross-team dependencies on dates, and see where the work lands against the deadline. If it does not fit, this is the cheapest moment you will ever have to change the scope, the date or the team. Make that call now, with the person who owns the deadline in the room.

Day 10: how you will work together. Agree the working agreements that stop the project drifting back into silos:

  • one backlog for the product, not one per team
  • one demo every fortnight, with all teams showing integrated work
  • integration at least weekly, so the seams are tested early
  • who makes the call when teams disagree, and how quickly

Finish by presenting the plan back to the wider group and to whoever is paying for the project.

What you should have at the end

None of this needs to be long. A few pages, written in plain language, that everyone in the room has read and agreed to:

  • The outcome in one sentence, with how you will measure it.
  • In scope, out of scope, and the reasons for the hard calls.
  • The dependency map, with dates.
  • A release plan: the slices in order, with a range for when each lands.
  • The top risks, each with an owner and what you will do about it.
  • The working agreement between teams.

If a new engineer joining in month three could read this and understand what the project is for and why it is shaped the way it is, it is good enough.

Working with a non-technical product manager

Many product managers do not come from software, and they do not need to. What they need is to see trade-offs clearly enough to make good decisions. Two weeks together makes that much easier:

  • Show, do not tell. A dependency map on a wall explains why three teams cannot all start on day one better than any status update.
  • Talk in options and costs. “We can have both by March, or this one by January” is a decision a product manager can make. “It is complicated” is not.
  • Split ownership clearly. Product owns what and why. Engineering owns how and how long. The date belongs to both, and it gets set after the estimates, not before.

When the deadline really is fixed

Sometimes it is: a regulation, a contract, an event. That makes inception more important, not less. With the date fixed, scope is the only thing you can change, and inception is where you choose the scope on purpose instead of finding out in the last month what did not fit.

Two weeks feels like a lot to spend before any code is written. For a project with several teams, it is the cheapest two weeks of the whole project. If you would like help running one, or someone outside the organisation to facilitate it, email hello@byrenhigg.in.